Golden West Wind Park, Calhan, Colorado

C2 Consulting is acquiring a 230kV electric transmission line right of way from the Wind Park to the substation grid connection. As part of this project C2 negotiated and acquired wind turbine easements over thousands of acres, planned and participated in public hearings and gave testimony before permitting authorities. Effort included extensive title work (both curative and investigative), permitting support, negotiation of sound and setback easements, coordination with Mountain View and Tri State utility companies, and permitting support.

Client: Kathleen Fay, Clipper
Windpower 805 708 2818
916 798 4453


Wind Turbine